Building 4 Foundation Repair*
The biggest structural problem with Northface Resort involved the foundation of Building 4. The original foundation was structurally unsound. Under the oversight of Frank Hogg, Northface Board President, Building 4 was jacked up, moved into the parking lot, and the foundation replaced during the months of September and October 1994.
Click here for the write-up of Building 4 in the Conway Sun (8 Oct 94)
Building being jacked from the foundation |
Building off foundation and supported by I-Beams |
|
Sliding Building into the parking lot |
The old slab foundation did not need to be demolished - it fell apart when the building was moved - note the total lack of steel rebar in the concrete |
|
The first of 24 pylons driven into the ground to provide stability for the new footings |
Capping the pylons with concrete |
|
New footings complete |
Forms top pour the new concrete walls - this time the foundation will have steel rebar to hold the concrete |
|
Setting I-Beams across the foundation |
Ready to move Building 4 back on its foundation |
|
Ready to lower the building back on its new foundation |
Finishing touches |
Thanks Board of Directors, in particular, Frank Hogg, President during this project, for the seemingly endless hours volunteered to orchestrate and oversee this project.
October 8th, 1994 - Conway Sun
----------------------------------------------------------